Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Daniel, Peter, Estela, Matt, Anmar

MINUTES

  • Introduction

  • Peter confirmed that so far, everyone has an A2 revision. Waiting on the FW from Ben (ETA 2 weeks)

  • Todd and Daniel like to remind engineering not to bad mouth the AVA platform and stick to the engineering tasks. Real complains should be discussed and shared internally with Arm and not in the public project

  • Review current infra (Wiki, JIRA, Slack, Email, gitlab)

    • Slack invitations were sent. Please followup with Arm IT to get them approved

    • Plan to invite Ben and Kasper as well to all the above infra pieces

  • Review current: Sprint 2

  • We will be ordering HW. However, we Don’t plan on doing inferencingusing them for inferencing (at least not in the foreseeable future)

    • Peter to get an Nvidia card for his machine

  • Board used for the CI setup (destined to Antonio in Brazil) is delayed. We are granting him remote access to help speed things along

  • Kasper is back Monday so we need to plan a call with him to get the needed info to get OpenAD Kit.

  • Need an NDA with ADLink

    • AI: Daniel to send out an introduction for Anmar to pursue the NDA aspect

  • Visit to Cambridge 25-29 of July

  • Automotive Blueprint is a LEDGE directed project

    • Arm controls the scope

    • Will follow current Linaro project’s reporting structure (monthly engineering report)

    • Announce the project to the LEDGE members

    • public access status

  • EWAOL Discussion

    • AI: Anmar to add it to the agenda for next week

  • Monthly billing mechanics

    • Linaro accounting to send an email to Arm with the milestone details for billing

ACTION ITEMS

...

  • AI: Ben has a bunch from previous email thread especially about getting autoware up and running on the AVA platform

    • Daniel and Ben already talked. work in progress