Highlights

...

This page is in progress and will be published in the second week of June

...

  • 2023 Roadmap is defined with strawman dates

  • Presented BOF at Connect with interest from Arm and TI

  • AMP Virtio work has began

  • Setup AMP Virtio testbed with Dual QEMU with IVSHMEM

    • Both use Cortex-A53 today (IVSHMEM is PCI based)

    • Testing with Zephyr on both sides

    • Will apply to RTOS + Linux as well

    • Testing w/ RPMsg

  • 3 KV260 boards w/ production SOMs were modified and 2 were sent to UK lab

Issues/Changes

  • Vacation will occupy the first week of May for several contributors

Plans

  • Define an outline of 2023 roadmap

  • Align roadmap dates at Connect with stakeholders and resource owners

Stretch Goals

  • Refresh the OpenAMP demo containers

  • Build virtio-exp branches of openamp libs, zephyr, and kvmtool in ci-builds

  • Submit OpenAMP CI jobs to LAVA lab (STM32MP157x-dk2 & KV260)On the Roadmap, not getting as much help as expected/hope from external contributors

    • Not redefining dates or goals yet but there is a danger of that

    • Most likely outcomes is that we will not do all the protocols and leave some for people to add as they need them

  • KV260 taken to Connect went bad at the venue. A replacement has been made.

Presentations & Documents:

See above for the Linaro Connect AMP BOF presentation.

Work completed this month

Jira Legacy
serverSystem JIRA
columnskey,summary,type,due,assignee,status,resolution
columnIdsissuekey,summary,issuetype,duedate,assignee,status,resolution
maximumIssues20
jqlQueryproject = HPP AND status = Closed AND resolved >= "2023/0405/0301" AND resolved <= "2023/0506/0111"
serverId59107c6f-1e52-32bc-b58f-400d54bba998

...