Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

View file
nameSDI lead project.pdf
height250
View file
nameSDI Lead Project Proposal - April 2018.xlsx
height250

Summary


LEG Representatives,

...

Worksheet 1 SDI Prioritisation

  • Default option - keep going

Current level of resources

  • WP0 - OpenStack Gate testing boost

200 new VMs means: 1600 vCPUs, 1600  GB RAM, 16 terabytes of storage

3 engineers full time for 1 year

  • WP1 - Libvirt enablement Arm64

1 engineer full time for 1 year

  • WP2 - Extra configurations testing OpenStack 

1 engineer per extra configuration chosen for 1 year

  • WP3 - Extra project enablement work OpenStack

See: /wiki/spaces/SDI/pages/16985686848

1 engineer per new project elected

  • WP4 - Scalability Testing OpenStack

20 engineers for 1.5 years

  • WP5 - Ceph CI

New lab: 10 Arm 64 servers

1 senior Ceph engineer and 1 QA engineer for as long as it takes to get it done. Maintenance 0.5 engineers going forward.

  • WP6 - Scalability Testing Ceph

15 engineers with Ceph field experience

  • WP7 - Containers Technology

1 senior engineer to scope the work, depending on scope the team will be sized

To vote for prioritisation please vote Yes or No for each column.

...