Summary


LEG Representatives,

...

Worksheet 1 SDI Prioritisation

  • Default option - keep going

Current level of resources

  • WP0 - OpenStack Gate testing boost

200 new VMs means: 1600 vCPUs, 1600  GB RAM, 16 terabytes of storage

3 engineers full time for 1 year

  • WP1 - Libvirt enablement Arm64

1 engineer full time for 1 year

  • WP2 - Extra configurations testing OpenStack 

1 engineer per extra configuration chosen for 1 year

  • WP3 - Extra project enablement work OpenStack

See: /wiki/spaces/SDI/pages/16985686848

1 engineer per new project elected

  • WP4 - Scalability Testing OpenStack

New lab: 1000 servers

20 engineers for 1.5 years

  • WP5 - Ceph CI

New lab: 10 Arm 64 servers

1 senior Ceph engineer and 1 QA engineer for as long as it takes to get it done. Maintenance 0.5 engineers going forward.

  • WP6 - Scalability Testing Ceph

New lab: 1000 servers (can be shared with WP4)

15 engineers with Ceph field experience

  • WP7 - Containers Technology

1 senior engineer to scope the work, depending on scope the team will be sized

To vote for prioritisation please vote Yes or No for each column.

...

MemberWP0WP1WP2WP3WP4WP5WP6WP7

ARM

  





Huawei  





Qualcomm  





Cavium  





HXT  





Kylin  





Fujitsu Agree AgreeAgreeAgreeAbstainDisagreeDisagreeDisagree
Red Hat  





Linaro   Agree AgreeAgreeAgreeAgreeAgreeAgreeAgree
Total