Milestone | Planned Date | Status |
---|---|---|
Aug 4, 2022 | Delayed due to AWF moving Open AD Kit host images from dockerhub. No ETA was given as to when they will be made available and where as of Aug 3, 2022 | |
M.22.A2 Start integrating AVA Dev Platform into Lava | Sep 1, 2022 | Work started by using the RockPi 4 board instead due to delay in delivering the AVA platform to CI engineers responsible for the CI. The delay is caused by Brazilian customs agents |
M.22.A3 Xen Hypervisor support on AVA platform enablement
| Oct 6, 2022 |
|