July 28st weekly call minutes

PRESENT

Rod, Daniel, Estela, Peter and Anmar

MINUTES

  • Summary: M.22.A1 milestone is progressing well We are now able to get OpenAD Kit 1.0 on AVA (no Xen) along with documentation.

  • Still need to convert the docs to github markdown as agreed with Matt Spencer. Should have that done by end of next week so A1 will be delivered ontime.

  • Next milestone (M.22.A2):

    • M.22.A2 - Start integrating AVA Dev Platform into Lava Integration CI lab as originally captured in the SOW with the goal at the end of month 2 to demonstrate and have documented how to integrate AVA Dev Platform integrated into the Lava CI infrastructure.

      • Risk: Antonio has yet to receive his platform so we can start the work. However, we are unable to confirm the completion of this work by month’s end

      • Dependency: new firmware update from ADLINK (updates?)

      • Suggestion: While the CI team is looking into integrating the AVA platform into LAVA, we suggest starting M.22.A3 (Xen on AVA w/Dom0 + DomU Linux + DomU Linux) which is focused on replicating M.22.A1 but with Xen.

        • Daniel: On board with the idea.

    • Alignment: Capturing the documentation on how to add the AVA platform into the integration lab is